250,000 PPH PACKAGE BOILER PROJECT PROFILE
CLIENT: Weyerhaeuser Paper Company
LOCATION: Springfield, Oregon
The scope of this project was to:
1) Study present plant steam production and usage during critical periods to determine the additional boiler requirements.
2) Equipment required on the boiler to meet present and future EPA requirements.
3) Total scheduling from selection through start up.
4) Boiler selection.
5) Provide dual fuel equipment.
6) Provide budgetary costs.
7) Total engineering for boiler installation.
8) Start up assistance.

The following engineering skills are required in this project:
- Plant Process Evaluation
- Emission Requirements
- Emission Controls
- Budget Controls
- Project Scheduling
- Project Management
- Complete Understanding of Steam Generation and Control
- Foundation Design
- Building Design
- Structural, Including Free Standing Stack
- Electrical
- Instrumentation and Controls
- Burner Management
- Flame Safety
- Piping Design
- FM and Insurance Carrier Requirements for Boilers
- Valve Sizing and Requirements
- Start Up
- Drawing Requirements and Standards